Project Details

Client:
Avtodor State Company

Country:
Russia

Practice Area:
Transport Infrastructure

Services:
Project Management and Works Supervision

Design Review and Construction Supervision for “Start-up Complex N°4 of the Central Ring Road (CRR) of Moscow”

The project is a PPP between the Highways State Company (Avtodor) and South-East Highway, the Concessionaire, aiming at the construction of the start-up complex No. 4 of the Central Ring Road (CRR).

This project comprises a 97 km heavy duty asphalt-concrete road with four 7.5 m lanes and an estimated traffic speed of 140 km/h. It will have 66 bridge structures, 49 flyovers and 7 traffic interchanges on different levels.

The investment value of this section is roughly 1.1 billion Euro.

IRD Engineering provides supervision of works as “Technical Expert”:

  • Reviewing and enhancing the design documentation in accordance with the laws of the Russian Federation;
  • Construction control, aimed at realization of the Concession Agreement and the works contract concluded;
  • Monitoring compliance of the construction carried out by the General contractor with the schedule for the works contract, and quality of work. Verification of conformity of the materials;
  • Carrying out the inspection measures undertaken by the General Contractor and/or the Concessionaire, to eliminate the defects of roads;
  • Preparation of opinions in relation to disputes between the Grantor/ Concessionaire/ General Contractor and third parties.